Skip to content
(02) 8000 0000
Construction Website

Home  /  Projects

Twelve years of work, and what each one taught us.

Every project below lists what it cost, how long it took and what went sideways. We'd rather you saw that than a gallery of hero shots.

Recent work

Nine projects, four sectors.

Case study — Wharf Road Commercial

The slab we poured out of order.

Tidal groundwater, a single-lane access road and a tenant who needed the ground floor trading by March. We brought the slab forward, worked the upper levels around it, and handed over eight days early.

What happened

Geotechnical came back with tidal influence two metres above what the original report assumed. The conventional sequence — dewater, pour the whole ground slab, then go up — would have cost us six weeks waiting on tides and pump hire.

So we split the slab into three pours and started the upper-level structure over the completed sections while the last third was still being dewatered. It meant more formwork and an argument with the engineer, and it bought back five and a half weeks.

The tenant traded from the ground floor on 3 March. We were off site eight days later.

Full project
ClientKestrel Property Group
ArchitectHale & Doyle
ContractDesign & construct
Value$8.4m
Program54 weeks
Variations3, totalling $91k
Defects at handover7
CompletedMarch 2025

“We've used four builders on this portfolio. Brayford is the only one who told us about a problem before it cost us money.”

Alira Nguyen — Asset Manager, Kestrel Property Group

Across the portfolio

186 Projects since 1994
97% Completed on or before program
1.9% Average variation value
0 Disputes since 2011

Next step

Want the references that go with these?

We'll give you the client's number for any project on this page. Ring them without us on the call — that's the point of a reference.